Track Construction:-
The track concept is based on the use
of 900WB 175 welded beams which are commercially available.
These beams are manufactured using steel plates and a continuous welding machine and will be fabricated in a specially built factory in a suitable location at the start of
the first line.
After fabrication, they will be transported along the newly constructed MonoCab VRT
track for erection. This will significantly reduce construction costs
and disruption to traffic. At the site, they will be erected using bridge
construction techniques.
Computer Integrated Manufacturing:-
The manufacture of the tracks will be enhanced by the
adoption the "CIM Steel" system (Computer Integrated Manufacturing) that has
been recently developed and adopted in Europe. In this process, the geometry of the steel is developed and structurally analysed in the engineer's office.
The final design data is then transmitted electronically directly to the
fabrication shop for fast, computerised, "just in time" manufacture and
immediate delivery to the site. This process will give significant time
and cost benefits.

Arterial Roads:-
The columns will be 750 - 900 mm diameter steel erected on suitable foundations at approximately
30 metre centres in the medians as shown on the left and below.
As a general rule there are few services in the medians, hence minimal changes to existing
infrastructure will be required with the resultant cost and time benefits.
Overhead power lines and street lights will normally be the only services effected. The minimum
clearance under the track will be 5 metres with a minimum of 6 metres at existing intersections to guard against
impact from high loads.


Roads with No Medians:-
Where there is no median, the track can be erected as shown on the right where it is passes
through an existing shopping precinct.
Points:-
At each station/stop, this points system allows a car to be taken
off the main line and not impede through traffic. Cars either side of
the car stopping will have their speed varied to allow sufficient time for
this operation. As a general rule, it will only be at these locations
that any land acquisition/resumption may be required, once again, with cost and time benefits.
Gold Coast Track Layout:-
The tracks will be located on every arterial road and highway. Preliminary
estimates indicate that approximately 200 km of track will service the Gold
Coast from Coomera to Coolangatta between the Pacific Highway (M1) and
the beach.
MonoCab VRT
Stations....
|